Vote YES September 25, 2001 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Report of the Public Facilities Input Committee to the Cedar Grove Board of Education
|
| Joanne Bell | Marylynn Benanti | Rick Bond |
| Patrick Byrne | Michelle/Louis Cammarata | George Corbo |
| Quin Cornman | Jim Cunningham | MaryBeth/Michael D’Argenio |
| Joseph DeBlasio | Steve DeCorte | Pete Dorman |
| Michael Frey | Angie Fusco | MaryAnne Gallagher |
| Andy Garcia | Neil Gerard | J.D. Hill |
| Paul Jacobovitz | Keith Kawecki | William Kowalski |
| Matt Kudla | Wendy/Gerry Lamb | Janice Lane |
| Claire Levash | Mary/Joe Ligas | Heather/Paul Maione |
| Cheryl/Sean McCabe | Frank Mandala | Robert McCurley |
| Kim McDermott | Joseph Moroney | Cindy Newkirk |
| Eileen O’Connell | Jackie/Russ Pagano | Anthony Palma |
| Michael Passafiume | Craig Peterson | Eileen Rendeiro |
| Robert Rickert | Rosemarie Rosamilia | Sal Rosamilia |
| Evan St. Lifer | Dennis Sedaille | John Sidebottom |
| Irma Solomon | Frank Starrett | Phyllis/Joseph Torlucci |
| Robert Van Etten | Denise Zangoglia | Theresa Zatorski |
| Raymond Zee | ||
| Matthew Hopkins | Donna Thompson | Judith Merz |
| Board Member | Board Member | Superintendent/Facilitato |
*Italics indicate those who attended most consistently
Work of the Committee
The goal of the committee was to provide recommendations to the Board of Education to remedy the school population growth problem. These recommendations were to be based on an open and thorough analysis of a wide variety of options.
To this end, the committee met 14 times during the period
of April 13 to August 15.
Specific subcommittees met 3 times. Activities included the following:
1) enumerated key principles in looking toward a new referendum (Appendix A).
2) enumerated key parameters for decision making (Appendix B).
3) delineated information needed by the committee; this information was provided as the process went forward.
4) carefully defined the facilities resources of the district: buildings, fields.
>physically toured MS/HS, LRP
>"walked through" every building via floor
and site plans
>identified issues at each site
5) generated a list of plans to be considered (Appendix C); this included input from the public and staff, who were invited to submit suggestions to the committee.
6) examined population projections (Appendix D) to more fully understand capacity needs in each building in each plan.
7) developed two formats for viewing and analysis of the options.
>quantitative, based on costs
>qualitative, based on information that
shapes perceptions of strengths/weaknesses of each plan
8) met with the district asbestos consultant to understand issues and costs relative to asbestos abatement (Appendix E).
9) met with the architect as needed.
>to understand basic issues of cost per square foot, advantages/drawbacks of different kinds of development
(for example, vertical build), ADA requirements, state
requirements, site issues
>to review specific plans and cost estimates for the
full range of options
10) developed several surveys to gather input from public.
>researched formats/costs for professional survey
>developed consensus on student surveys relative to
middle school
>conducted and collated student surveys
(Appendix F); results reported to board of education on June
27th, 2000.
>implemented survey to the public (Appendix G)
>analyzed data from survey of the public
>reached consensus on Executive Summary of
survey data (presented by superintendent at Aug. 22, 2000
board of education meeting) (Appendix H)
11) generated and refined the Options Evaluation Matrix based on extensive questioning and refinement.
12) received and reviewed a variety of individual options, views, and perspectives submitted in writing; engaged in considerable discussion of individual options, views, and perspectives.
13) via analysis, narrowed the full range of options to three "sets" of options for ongoing consideration. At the direction of the board, which received an update of PFIC activities on June 27th, 2000. These options were then questioned, refined, and examined in great detail.
Subcommittee on the Option Evaluation Matrix met twice with the architects to refine costs and ensure comparability of analysis of options (see pages 33-34).
At direction of the board, Qualitative Evaluation of Options chart (see pages 35-36) was reconfigured to be primarily fact-based rather than opinion-based (i.e., rather than listing advantages/disadvantages).
Individual members submitted detailed questions/concerns to the architect for resolution.
Full committee reviewed options in detail and raised further questions/issues for refinement.
Full committee generated lists of "qualities" of each plan (positives/negatives; strengths/drawbacks; pros/cons; pluses/minuses) which were developed into an addendum to the Qualitative Evaluation of Options chart (see pages 37-38).
At request of committee, architect updated facilities upgrade costs for board consideration (see pages 23-32).
14) received copies of research done by individual committee members and/or heard presentations of research by individual committee members.
15) developed consensus on presentation of report to the board of education; subcommittee formed to assist presenters in preparation.
These activities are documented by agendae and summaries.
The following plans (not in this file on website) represent DiCara/Rubino Architect’s conceptualizations for the various configurations. The cost presentations represent figures for budget purposes. It is understood that these plans and projected figures are for planning purposes only. Both plans and budget estimates are subject to further refinement by the Board of Education.
For clarity:
The architect presents these plans for the board’s planning purposes only.
Whatever plan the board of education selects must be reviewed by State offices. As part of the planning services, the architect will help the board to prepare for this review of educational sufficiency.
The architect is not "bidding" on the actual construction of whatever plan is chosen. The architect’s fees for this planning service are not tied to eventual construction in any way.
Once the board of education decides on a particular plan, construction is subject to the bidding process--that is, it is open to all interested parties.
The Option Evaluation Matrix was devised as a way for the committee to look at the costs relative to various plans that were considered. (Please note that this original information did NOT include any state funding; nor did it include work subsequently done by the board to reduce various costs.) The matrix provides an "apples to apples" view of each plan, delineating specific costs for each building of each plan and projecting ongoing costs for each implementation scenario.
Options are listed and briefly defined across the top of the matrix.
The left margin column provides cost breakdowns for each school involved in any given option. Below the heavy black line is a "Construction Subtotal"—adding all the costs in that column for that option.
The next row adds the 30% soft costs that are projected for each option. (Soft costs include such items as architectural and engineering fees; application fees; permits; studies and surveys as needed.) Adding this row to the "Construction Subtotal," leads to the "Construction Total."
Beneath the "Construction Total" appear additional annual costs. The first set, "Lost Annual Revenue," reflects the rental income that will be lost if LRP or RR is reopened. "Additional Annual Costs" include additional administration needs, operational costs (custodial, maintenance, utilities), and mandatory busing. The cost of additional staff was not included because most staff additions will be driven by changing enrollments rather than by configuration. Furthermore, programmatic staff additions will be comparable across the options. The row "Annual Costs/Revenue Lost" provides a total for the ongoing costs of each plan.
The row entitled "Annual Total (PV Factor)" brings the ongoing costs to a "Present Value." This is a recognized accounting procedure to help compare current costs to costs over time. (Note: The present value factor translates into practical application in the next set of figures presented on the matrix.)
The final set of information on the matrix translates the construction costs and annual costs into the cost to the average taxpayer. This information is broken out into the cost for the bond (construction costs) and the cost on the annual budget (ongoing costs). The bottom line of the matrix provides the total cost to the average taxpayer. Again, this line provides the practical application of the Present Value calculation above.
In addition to looking at fiscal issues via the Option Evaluation Matrix the committee also wanted to provide information about other factors or elements that need to be considered in selecting an option. At the board’s request, the committee limited information on the chart to facts rather than opinions based on those facts.
The Addendum to the Qualitative Evaluation of Options Chart provides some of the implications of the information on the chart itself.
Considerable discussion of the options occurred during PFIC committee meetings. The "argument" relative to each option is summarized on the next several pages. The points made represent opinions expressed by members of the PFIC.
It should be noted that the administration has consistently maintained that the quality of a school district rests first and foremost on quality curriculum and quality personnel to deliver that curriculum. Nothing in the following "arguments" is meant to override this basic consideration.
Proponents of the K-4, 5-8, 9-12 plan emphasize the following:
This plan will allow improvement of the K-4 program through availability of art and music rooms.
This plan will allow improvement of the 5-8 program through implementation of a true middle school philosophy:
Electives
Exploratories
Guidance
Advisories
This plan provides the best focus on the developmental needs of "tweens," students between childhood and adolescence.
This plan provides efficiencies through consolidation of resources.
Efficient division of classes
Efficient balance of classes
Efficient use of specialists
This plan aligns program with the State’s Core Curriculum Content Standards organization and assessment (K-4, 5-8, 9-12)
This plan provides middle school and high school with separate identities.
Provides real transition from middle to high school
Allows high school to function independent of middle school constraints
This plan is less susceptible to enrollment trend shifts than the K-6 plan.
Critics of the K-4, 5-8, 9-12 plan emphasize the following:
The Grades 5-8 configuration is not necessarily "the best"
Other districts use various other configurations successfully
Star Schools/Blue Ribbon Schools do not include 5-8 schools
This plan creates traffic/safety concerns due to student numbers and locations
Approximately 238 cars anticipated for drop-off and pick-up
Either site located on main road (LRP heavily trafficked; RR 40 mph speeds)
This plan removes grades 7-8 from the high school setting
Less efficient because core facilities must be duplicated in new setting
Eliminates support of 9-12 programs (such as music) by middle school
Lessens contact with positive 9-12 role models
This plan focuses on middle school facilities and does not affect other building facilities in the district.
Proponents of the K-4, 5-6, 7-8/9-12 plan emphasize the following:
This plan can provide many of the benefits of the 5-8 plan (such as team teaching, guidance) in a more cost effective manner.
This plan will allow improvement of the K-4 program through availability of art and music rooms.
This plan will allow improvement of the 5-6 program through consolidation of resources for those grade levels.
A Grades 5-6 school will permit focus on the developmental needs of these youngsters.
Grade 5 students should not be together with Grade 8 students in a building.
This plan is the less costly than the 5-8 option. At LRP, $4.075 million less; at RR, $2.490 million less.
Maintaining grades 7-8 in the high school facility allows use of that building’s core facilities.
Auditorium
Gymnasium
Cafeteria
Media center
Critics of the K-4, 5-6, 7-8, 9-12 plan emphasize the following:
A 2-year school is not the most desirable for students.
Negatives of 2-year sequence documented in research literature
Insufficient time for students to acclimate to school.
Insufficient time for teachers to develop familiarity with students.
Negative impact on achievement scores noted
This plan does not remove grades 7-8 from the high school setting
12-year-olds are in the same building with 18-year-olds
Proximity provides the opportunity for younger students to see negative behaviors (smoking, use of foul language, drugs & alcohol, sexual activities)
Proponents of the K-6, 7-8, 9-12 plan emphasize the following:
This plan, currently in use in the district, has a positive track record.
Achievement test scores are consistently strong: 25% above national average
Scores on the state tests are strong: GEPA 96% proficient lang. Arts; 75% mathematics
SAT scores are strong: 1999 average 1032; 95% of class taking test; 33/43% average scores were 1118-1295.
Cedar Grove students are accepted to a wide variety of colleges/universities
This plan will allow improvement of the K-6 program through availability of art and music rooms.
A third K-6 school will bring back the "neighborhood schools" concept.
A third K-6 school is most likely to minimize busing issues.
Plan 7C permits the most positive distribution of traffic.
This plan is the least costly: At LRP, $4.7 million less than 5-8; $630,000 less than 5-6 (construc.)
At RR, $3.376 million less than 5-8; $886,000 less than 5-6.
Maintaining grades 7-8 in the high school facility allows use of that building’s core facilities.
Auditorium
Gymnasium
Cafeteria
Media center
Benefits projected for 5-6 can be applied within K-6 as well as 5-8.
Critics of the K-6, 7-8, 9-12 plan emphasize the following:
Having a 3rd K-6 school is the least flexible option
Dividing school populations among 3 sites instead of 2 is more likely to lead to unbalanced classes and/or single classes at a grade level.
The benefits of our current K-6 schools (in terms of achievement) may derive from having multiple sections at a grade level; this could be lost with 3 K-6 schools.
Redistricting would be needed, possibly every year, to maintain balances.
This plan does not remove grades 7-8 from the high school setting
12 year olds are in the same building with 18 year olds
Proximity provides the opportunity for younger students to see negative behaviors (smoking, use of foul language, drugs & alcohol, sexual activities)
Home | Current School Problems
| Results of CG Survey
Facilities Options Report | Proposed Referendum
| FAQ's
Other Studies | How You Can Help
| References & Links
Contact Us | About CQE
Disclaimer: Information on this site has been ascertained through various public sources and is provided in the best interest of the Cedar Grove community.
Paid for by the
Citizens for Quality Education.
257 Cedar Street
Cedar Grove, NJ 07009
Need a web site? Contact the webmaster
or visit our web site at www.OK2try.com.